Replying to an RFI

To Reply to an RFI

There are two options to reply to an RFI.

 

Posting a Reply

Bring up the RFI Log

RFI Log for Click In

 

Click on the RFI Number you wish to respond to and follow instructions above.

 

Note:  If you forward a RFI to a third party from the root level, it will give the forwarded RFI the next number in the log sequence.  It will not create a new numbering sequence.

 

You should insert your response in the Replies field ( Bottom of form )

 

Posted Reply Open Issue

 

You have the option to either save your response or post the response.

 

To Save – click on the Save icon   Save Response Icon

 

To Post – click on the Post icon Post Response

 

The Post icon will lock the architect’s response showing name, date, and time of posting.

 

Posted Reply Open Issue

 

RFI Response Admin View

 

RFI Manual Answer Entry

 

 

Type your reply in the Answer field
From – will default to the user; can be modified
RFI Status – select status via the drop down box.
Transmit the RFI back to the subcontractor. (Note:  Make sure to change to TO and FROM fields prior to returning to the subcontractor)

 

Note:  You have the option to fax the RFI as well, but you must also transmit the RFI in order to keep the report data current.

 

The posting process will send a notification to the GC - CM PM of the RFI response.