CREATING A SUBMITTAL PACKAGE
• | Click on Create New Submittal Package icon ![]() |
• | Package Screen comes up |
• | Number – insert Package Number |
• | Description – insert package description |
• | Reviewing Company – defaults to architect setup in project information; can be modified |
• | Project Manager – defaults to the GC - CM Project Manager setup in project information |
• | Submitting Subcontractor – insert subcontractor name via selection button |
• | Notes – insert if applicable |
• | You have the option to attach a file or document to the package: |
** These Entries control BIC ( Ball in Court ) for the submittal details report **
When all information has been entered, click the Save Button via the drop down box . You will have the option to Save, Save & New and Save & Copy.
Once the submittal package has been created, the program will take you back to the submittal log main screen.