Creating a Submittal Package

CREATING A SUBMITTAL PACKAGE

 

SumbittalHeader

 

 

Click on Create New Submittal Package icon NewSubmittalPackage
Package Screen comes up

CreateNewSubmittalPackage

 

Number – insert Package Number        
Description – insert package description
Reviewing Company – defaults to architect setup in project information; can be modified
Project Manager – defaults to the GC - CM Project Manager setup in project information
Submitting Subcontractor – insert subcontractor name via selection button
Notes – insert if applicable
You have the option to attach a file or document to the package:

** These Entries control BIC ( Ball in Court ) for the submittal details report **

 

NewSubmittalPackageFinal

 

When all information has been entered, click the Save Button via the drop down box .  You will have the option to Save, Save & New and Save & Copy.

Once the submittal package has been created, the program will take you back to the submittal log main screen.

 

Submittal Summary Screen